Ore Yard Project of A Gangchi has been partially put into use in the winter

Date:2011-12-03 10:33  PV:993


     Wild north wind, swirling snow, brought the breath of winter, it also brings people look forward to spring.
Standing in the cold, looking forward to the arrival of warm spring. At Ore Yard Project of A Gangchi, a cold wind blowing, blowing people have nowhere to hide.
However, in this environment, the project still insist, 2011 ending to facilitate the Bayuquan winter storage arrangements.

     Before the lay-off in November, Its has completed most of the construction tasks. Today, BQ1 and BQ2 track beam rail and civil construction has been completed.
BQ5 rubble retaining wall masonry has been completed 700M; The the 1-7 yard one and two-story water stable all construction is completed in the yard construction, 2-5 yard has been put into use, according to the Bayuquan the requirements, to facilitate the storage of of Minato winter supplies, overtime completed. The 8-9 yard with a layer of water-stable complete, two-story water stable construction of approximately 53,000 square; 10 yard gravel construction has been completed. Loading line track beam belt base
   Wild north wind, swirling snow, brought the breath of winter, it also brings people look forward to spring. Standing in the cold, looking forward to the arrival of warm spring. The cold wind blowing, blowing people have nowhere to hide
However, in this environment, the project still insist, 2011 ending to facilitate the Bayuquan winter storage arrangements.

     Before the lay-off in November, its work has been completed most of the construction tasks. Now, BQ1 and BQ2 the track girders rail and civil construction has been completed; Beam rail, BQ3 and BQ4 track, laying to 480M, the construction of civil works has been all over; BQ5 rubble retaining wall masonry has been completed 700M; 1-7 in the yard construction yard one and two-story water stable all the construction is completed,
2-5 yard has been put into use, according to the Bayuquan the requirements, to facilitate the storage of of Minato winter supplies, overtime completed.
The 8-9 yard with a layer of water-stable complete, two-story water stable construction of approximately 53,000 square; 10 yard gravel construction has been completed. Loading line track beam belt base


 